LNG and Gas Sector

LSP - Feasibility study and Basic design Verification

Main Material Tanks (Ethane) construction work for the Petrochemical complex in South of Vietnam

Project OwnerLSP
Year of implementation2025
LocationVung Tau province
Investment cost400 mil. USD
SoWFeasibility study and Basic design Verification

ITECO Northern LNG Terminal Project

Provision of LNG to Industrial and Transportation Customers

Project OwnerGas South
Year of implementation2021
LocationHo Chi Minh, Binh Duong, Dong Nai, Long An
Investment cost~ 10 mil. USD
SoWFeasibility study, basic design (15 stations) and detailed design (8 stations), QRA & safety study

Provision of LNG to Industrial and Transportation Customers

Project OwnerGas South
Year of implementation2021
LocationHo Chi Minh, Binh Duong, Dong Nai, Long An
Investment cost~ 10 mil. USD
SoWFeasibility study, basic design (15 stations) and detailed design (8 stations), QRA & safety

TAN VIET LNG REGASIFICATION STATION

Project OwnerTAN VIET METAL TECHNOLOGY COMPANY LIMITED
Year of implementation2024
LocationNghe An
Investment cost~ 1.5 mil. USD
SoWDetailed Engineering, Firefighting prevention engineering, Total cost estimate

Nha Trang LPG Filling Station

Project OwnerGas South
Year of implementation2022
LocationNha Trang city, Khanh Hoa province
Investment cost~ 2 mil. USD
SoWDetailed engineering and cost estimate

Gas Pipeline

Gas Pipeline for upgrading of gas supply capacity at Nhon Trach Industrial Park and Low-pressure gas supply system for Phuong Nam Roof Sheet Plant

Project OwnerPVGas D
Year of implementation2022
LocationNhon Trach district, Dong Nai province
Investment cost~ 1.3 mil. USD
SoWFS and basic design

Gas Receiving Station

Gas receiving station for Global Vietnam Aluminum plant Phase 1 & Phase 2

Project OwnerGASTECH
Year of implementation2019
LocationPhu My district, Ba Ria – Vung Tau
Investment cost~3.5 mil. USD
SoWTechno-economic report and detailed design, Owner Engineer, EPC

Nam Kim Gas Pipeline

Project OwnerGASTECH
Year of implementation2024-2025
LocationVũng Tàu
Investment cost~ 2 mil. USD
SoWTechno-economic report and detailed design Firefighting prevention